A guide to 'proceeding at risk'

4 min read
Oct '25 • by Heather

Quick summary

Proceeding at risk means starting your building regulation drawings before planning approval, which can save about 5-6 weeks and over a month and a half in total time. It might cost an extra £200-£300 plus VAT if alterations are needed due to planning rejection or conditions, but small changes can sometimes be free.

When it comes to your home, you probably want to keep risk out of the equation. However, in the planning and building regulations stage, a little risk can be your friend.

Proceeding at risk while you wait for the go-ahead from the council could shave months off your project’s timings, ideal for anyone raring to go or who has rental costs to consider. Interested? Here’s what you need to know…

What is proceeding at risk?

Proceeding at risk refers to starting your building regulation drawings before you have planning approval. It takes advantage of the 8-10 week waiting period homeowners must go through while a planning decision is made.

Why is time so important? Well, even with a great architect by your side (such as ourselves), you have so many third parties involved that, like planning, this is a time-consuming stage.

For example, Resi’s building regulations team are able to put together the necessary technical drawings within 2-3 weeks. However, because these drawings rely on the input from structural engineers and surveyors, waiting for this information will likely add 3 or more weeks to the timeline.

Therefore, by starting this process during the planning stage, homeowners are able to start construction as quickly as possible.